12 men can complete a project in 8 days. For the first two days, all 12 men reported for work but on the third and fourth days 2 men did not report for work. If in the following days, all 10 men reported for work, in total how many days the whole project was completed?

1
8
2
\(7\frac{1}{2}\)
3
\(9\frac{1}{5}\)
4
\(8\frac{1}{2}\)