In a small engineering project, for an activity, the optimistic time is 2 minutes, the most likely time is 5 minutes and the pessimistic time is 8 minutes. What is the expected time of the activity? 

1
1 minutes
2
5 minutes
3
8 minutes
4
18 minutes