In the network shown below, the critical path is ________
(The number on the arrow shows the duration of the activity)
1
1 – 2 – 3 – 4 – 5 – 6
2
1 – 2 – 4 – 5 – 6
3
1 – 2 – 3 – 5 – 6
4
1 – 2 – 4 – 3 – 5 – 6