In the Critical Path Method (CPM), the cost-time slope of an activity is given by
1
\( {\rm{\frac{{Crash\;Cost - Normal\;Cost}}{{Crash\;Time\;}}}} \)
2
\({\rm{\frac{{Normal\;Cost}}{{Crash\;Time - Normal\;Time\;}}}} \)
3
\( {\rm{\frac{{Crash\;Cost}}{{Crash\;Time - Normal\;Time\;}}}}\)
4
\( {\rm{\frac{{Crash\;Cost - Normal\;Cost}}{{Normal\;Time - Crash\;Time\;}}}}\)