engineering recuitment UPPSC AE Mock Test 2024 Industrial Engineering Operations Research PERT and CPM
Find the expected time of an activity with Pessimistic time (tp) = 14 days, Most likely time (tm) = 8 days, Optimistic time (to) = 2 days.
1
6
2
7
3
8
4
9