engineering recuitment NMDC Junior Officer (Trainee) Mock Test 2024 Power Systems Generating Stations Non Conventional Energy Source
Which of the following criteria for selecting the site for tidal power projects is INCORRECT?
1
The site should allow the development of the necessary plant for reasonable cost
2
It should be environmentally acceptable
3
The storage area should be large
4
The tidal range should be small and limited