engineering recuitment NMDC Maintenance Assistant Fitter 2021 Mock Test Quantitative Aptitude Time and Work
If 7 men working 7 hours per day for 7 days produces 42 chairs, then how many chairs 14 men will produce working 14 hours per day for 14 days?
1
336
2
324
3
350
4
328