A, B and C can complete the whole work in 12, 15 and 20 days respectively and with the help of D, they can complete the whole work in 4 days. What is the total share of B and D if the total payment received by them is Rs. 19,650?
1
Rs. 9,285
2
Rs. 9,170
3
Rs. 9,180
4
Rs. 9,270
5
Rs. 9,275