Ramesh and Suresh can complete a piece of work in 10 days and 12 days, respectively. If they are working on alternate days, starting with Ramesh, in how many days will the entire work be finished?

1
\({12}\frac{10}{11}\)
2
\({10}\frac{10}{11}\)
3
\({12}\frac{5}{6}\)
4
\({10}\frac{5}{6}\)