engineering recuitment BPSC AE Mock Test 2025 Construction Materials and Management Project Planning PERT
Which of the following statement is true for CPM when compared to PERT?
1
It is used for non-repetitive jobs.
2
It indirectly introduces the concept of cost into the analysis
3
It does not incorporate statistical analysis in determining time estimates
4
Under CPM convention, each event represented by a circle and arrows are used to indicate activities.