The following data is available for a cross-project
|
Parameter |
Canal |
Drainage |
|
FSL (m) |
108 |
109 |
|
Bed level (m) |
105 |
107 |
|
Discharge (m3/s) |
90 |
15 |
The most appropriate cross drainage work for this situation is:
1
syphon aqueduct
2
syphon
3
super passage
4
aqueduct