Radha can complete a piece of work in 3 days, while Raji can complete the same work in 2 days. Both of them complete this work by working together and get ₹150 as total payment for the work done. What is the share of Radha out of the above payment?
1
₹70
2
₹40
3
₹30
4
₹60