railway RRB JE (CBT I + CBT II) Mock Test 2024 Power Systems Economies of Power Generation Reserve Capacity
A power plant has a maximum demand of 15 MW. The annual load factor is 50% and annual plant capacity factor is 40%. The operating reserve capacity is
1
6 MW
2
3 MW
3
3.75 MW
4
7.5 MW