railway RRB JE (CBT I + CBT II) Mock Test 2024 Power Systems Economies of Power Generation Load Factor
An industrial consumer has a daily load pattern of 2000 kW, 0.8 lagging power factor for 12 hours and 1000 kW at UPF for 12 hours. The load factor is
1
0.875
2
0.75
3
0.65
4
1.00