railway RRB JE (CBT I + CBT II) Mock Test 2024 Industrial Engineering Operations Research PERT and CPM
A network planning method in which activity time could not be estimated because of uncertainty of activity timing, this acquired the shape of probabilistic model is known as:
1
Resource Programming and Scheduling Method (RPSM)
2
Programme Evaluation Review Technique (PERT)
3
Multi-Operation Schedule System (MOSS)
4
Least Cost Scheduling (LCS)