railway RRB JE (CBT I + CBT II) Mock Test 2024 Industrial Engineering Production Planning and Inventory Control Inventory Control
The break-even output for total fixed cost of Rs. 40,000, for which price per unit is Rs. 10, and variable cost is Rs. 5
1
6000
2
7000
3
8000
4
10000