Select the correct sequence of activities for a building construction:
1
1. Sub-structure
2. Design
3. Finishing
4. Super-structure
2
1. Design
2. Sub-structure
3. Finishing
4. Super-structure
3
1. Sub-structure
2. Design
3. Super-structure
4. Finishing
4
1. Design
2. Sub-structure
3. Super-structure
4. Finishing