railway RRB JE (CBT I + CBT II) Mock Test 2024 Power Systems Economies of Power Generation Reserve Capacity
The maximum demand on a power station is 25 MW. If the load factor is 60% and the plant capacity factor is 50%, calculate the reserve capacity of the plant.
1
15 MW
2
30 MW
3
5 MW
4
25 MW