Which of the following statements is not correct about PERT ?
1
Network is constructed based on the events.
2
It does not take uncertainties involved in the estimation of times.
3
Network deals with uncertainties and hence three time estimations are considered.
4
As there is no certainty of time, activity duration cannot be reduced.