railway RRB JE (CBT I + CBT II) Mock Test 2024 Industrial Engineering Production Planning and Inventory Control Inventory Control
Find the economic batch quantity for the given data: Annual requirement of parts 800, inventory cost 10% of value/year, the setup cost is Rs. 200 per setup and the cost per part Rs. 20.
1
400
2
500
3
800
4
200