railway RRB JE (CBT I + CBT II) Mock Test 2024 Industrial Engineering Operations Research PERT and CPM
The artificial activity which indicates that an activity following it cannot be started unless the preceding activity is complete, is known as-
1
Dummy
2
Total float
3
Event
4
Free float