The following table gives the data on five activities A, B, C, D, and E of a project.
|
Activity |
(Start-End) week number |
Resource needed/week |
|
A |
4 – 7 |
4 |
|
B |
6 – 13 |
7 |
|
C |
8 – 17 |
5 |
|
D |
12 - 19 |
4 |
|
E |
10 - 21 |
8 |
Find the maximum total resources load in any week, and the corresponding week:
1
24; (12-13) week
2
28; (11-12) week
3
24; (14-15) week
4
20; (12-13) week