The following table gives the data on five activities A, B, C, D, and E of a project.

Activity

(Start-End)

week number

Resource

needed/week

A

4 – 7

4

B

6 – 13

7

C

8 – 17

5

D

12 - 19

4

E

10 - 21

8


Find the maximum total resources load in any week, and the corresponding week:

1
24; (12-13) week
2
28; (11-12) week
3
24; (14-15) week
4
20; (12-13) week