railway RRB JE (CBT I + CBT II) Mock Test 2024 Construction Materials and Management Project Planning
Lead Time in materials/inventory management for a company usually refers to the:
1
Time required for only the dumping of material at the client place
2
Time taken to only order certain materials in a company
3
Time elapsed between ordering, receiving and putting the material into use
4
Time taken to create a product in a company