railway RRB JE (CBT I + CBT II) Mock Test 2024 Industrial Engineering Operations Research PERT and CPM
Slack represents the difference between the-
1
Proposed allowable time and the earliest expected time
2
Normal allowable time and the latest expected time
3
Latest allowable time and the normal expected time
4
Latest allowable time and the earliest expected time