After fixing the plane table to the tripod, the main operations which are needed at each plane table station are:
i) leveling
ii) orientation
iii) centering
The correct sequence of these operations is-1
(ii), (iii), (i)
2
(i), (ii), (iii)
3
(i), (iii), (ii)
4
(iii), (i), (ii)