Workers from company A are 1.25 times as efficient as workers of company B. Find the number of days taken by 8 workers of company B to complete the work that is completed by 12 workers of company A in 60 days. (Efficiency of workers of particular companies is the same)

1
110 days 
2
112. 5 days 
3
125 days 
4
150 days 