Ansh and Tanvi can do a piece of work in 24 days and 40 days, respectively. They started the work, and after 8 days, Shubham, who can complete the same work in 20 days alone, joined them. In how many days can the whole work be completed?
1
15 days
2
16 days
3
20 days
4
12 days