railway RRB NTPC Mock Test Series 2024-25 (CBT 1 + CBT 2) Quantitative Aptitude Time and Work Work Efficiency
A can complete the certain work in 5 days and B in 10 days. In how many days they will complete the work working together if A joined one day late and B leave 3 days before the completion of the work.