A man completes a work in 15 days by working 4 h per day for 5 days, 5 h per day for 5 days and 6 h per day for 5 days. If he works 8 h per day with half an hour lunch break he will complete the work in:
1
12 days
2
10 days
3
7.5 days
4
8 days