Teaching HPSC Lecturer (Technical) Mock Test 2024 Construction Materials and Management Project Planning
The total float can be expressed as
A. latest start time - earliest start time
B. latest finish time - earliest finish time
Identify the correct statement.
1
Statement B is true and A is false
2
Both A and B are true
3
Both A and B are false
4
Statement B is false and A is true
5
Question Not Attempted