SSC SSC JE Civil 2025 Mock Test Series (Paper 1 & Paper 2) Reinforced Concrete Structures Bond, Anchorage and Development Length
In case of unavailability of space for providing development length in an RCC beam which option shall NOT be used to satisfy the criteria of development length?
1
Bends
2
Chairs
3
Hooks
4
Mechanical anchorages