Teaching HPSC Lecturer (Technical) Mock Test 2024 Soil Mechanics and Foundation Engineering Seepage Analysis
Which of the following is/are the correct remedies to prevent piping failure of weirs?
Remedy 1: Providing sufficient length of the impervious floor so that path of percolation is increased and the exit gradient is decreased
Remedy 2: Providing pile at downstream end
1
Remedy 1 is correct while remedy 2 is incorrect.
2
Remedy 2 is correct while remedy 1 is incorrect.
3
Both remedies are correct.
4
Both remedies are incorrect.
5
Question Not Attempted