Teaching HPSC Lecturer (Technical) Mock Test 2024 Construction Materials and Management Project Planning
Which of the following statement is correct regarding PERT in network analysis?
I. In PERT it is assumed that cost is directly proportional to the time.
II. In PERT critical path is the path which joins the critical events.
1
Only I
2
Only II
3
Both I and II
4
Neither I nor II
5
Question Not Attempted