SPT is conducted at 3m below the Ground level and SPT number observed for first 150 mm penetration is observed as 8 while the SPT number observed for last 300 mm penetration is 31. If the effective overburden pressure at the test level is 300 kN/m2 and water table is present at 2.5m below the Ground level, then the final corrected SPT number will be

1
29
2
39
3
23
4
31