Which one of the following statements is NOT correct related to line-of-balance schedule ?

1
It represents both a presentation format and a scheduling technique.
2
It is a very visual method of representing a particular type of project.
3
It allows the planning team a sequence without any single option.
4
Using a combination of sloping lines, bars and blocks, operations can be sequenced so that space and resource conflicts are quickly identified and addressed.
5
Question Not Attempted

Sponsored

hivanix.in

Visit

This quiz is brought to you by hivanix.in

🌐 Web App Development

Quick Navigation