At a construction site, the reduced level of ground is 100 m and reduced level for bottom of footing is 98 m. The quantity of earthwork in excavation for 10 number of square footing of 2 m side is:

1
400 cu.m
2
40 cu.m
3
80 cu.m
4
800 cu.m