At a certain point in the floor of the weir, the uplift pressure head due to seepage is 3.75 m. If the relative density of the concrete is 2.5, the minimum thickness of the floor required at this point to counteract the uplift pressure.
1
3.33 m
2
1.50 m
3
2.50 m
4
3.75 m