The loss formula coefficient matrix for a two-plant system is given by
\(B = \left[ {\begin{array}{*{20}{c}} {0.001}&{ - 0.0001}\\ { - 0.0001}&{0.0013} \end{array}} \right]M{W^{ - 1}}\)
The economic schedule for a certain load is given as
P1 = 150 MW and P2 = 275 MW.
Penalty factor of plant 1 is _______.
1
1.324
2
1.515
3
1.575
4
1.721