SSC SSC JE Civil 2025 Mock Test Series (Paper 1 & Paper 2) Estimating, Cost and Valuation Measurement
Keeping in view, the feasibility order of magnitude, the preliminary, conceptual or budget estimates, are prepared by -
1
Construction manager
2
Owner himself/herself
3
Architect/engineer
4
All of the options