A parabolic vertical curve is set out connecting a +0.7% grade to a -0.6% grade. The chainage and R.L. of the point of intersection are 1000 m 250 m respectively. The admissible rate of change of grade is 0.05% per 20 m. The chainage of the tangent points will be
1
600 m and 1400 jm
2
650 m and 1350 m
3
700 m and 1300 m
4
740 m and 1260 m