Consider the following operations of preparation of brick earth:

1. Digging,

2.Weathering,

3. Tempering,

4. Blending,

5. Unsoiling

The correct sequence of these operations are:

1
5, 1, 4, 2, 3
2
5, 1, 2, 4, 3
3
1, 5, 2, 4, 3
4
5, 1, 3, 2, 4