A can complete a work in 8 days and B can complete the same work in 11 days. How long will they take, if both work together?

1
4\({12 \over 17}\) days
2
5\({12 \over 19}\) days
3
4\({11 \over 19}\) days
4
4\({12 \over 19}\) days