Statement I: In the payback period method, the risk of the project is adjusted by lessening the target payback period.
Statement II: Sensitivity Analysis helps in the calculation of net present value of the proposal
1
Statement I is correct, Statement II is incorrect
2
Statement I is incorrect, Statement II is correct
3
Both Statements I and II are correct
4
Both Statements I and II are incorrect