If 10 men can do a piece of work in 50 days, then how many men are additionally added to do the task in 20 days?

1
5
2
15
3
20
4
25

Sponsored

hivanix.in

Visit

This quiz is brought to you by hivanix.in

🌐 Web App Development

Quick Navigation