A contract on construction job specifies a penaity for delay in completion of the work beyond a certain date is as follows : Rs. 200 for the first day, Rs. 250 for the second day, Rs. 300 for the third day etc. the penalty for each succeeding day being Rs. 50 more than that of the preceding day. How much penalty should the contractor pay if he delays the work by 10 days ?
1
Rs. 4950
2
Rs. 4250
3
Rs. 3600
4
Rs. 650