Teaching EMRS Librarian Mock Test 2023 Library Science Management of Libraries & Information Centres Project Management
The minimum possible time required to accomplish a task, assuming everything proceeds better than is normally expected is called
1
pessimistic time (P)
2
optimistic time (O)
3
most likely time (M)
4
expected time (TE)