Choose the correct among the followings:

I. PERT/CPM and Gantt Chart show a graphic representation of work on a time scale.

II. PERT/CPM is the most widely used technique in project management.

III. PERT restricts its attention to the time variable whereas CPM includes time-cost trade-offs. 

1
Only I
2
I and II
3
II and III
4
I, II, and III