A, B and C together can complete a certain work in 40 days. B and C together can complete the same work in 60 days. B is 25% more efficient than A. A, B and C work together for 30 days. In how many days will B alone complete the remaining work?

1
20 days
2
24 days
3
30 days
4
32 days
5