Preeti can do a work in 36 days. Anu can do the same work in 30 days. If Preeti and Anu start the work together but Anu leaves the work 3 days before its completion, find the number of days in which the total work is completed.

1
18 days 
2
16 days 
3
14 days 
4
11 days 