Match the following
| List I ( PERT term) | List II ( Description) | ||
| A | Nodes | 1 | It refers to tasks without slack, which are crucial for project timeline adherence. |
| B | Fast-tracking | 2 | It denotes the duration by which a task can be delayed without affecting other tasks or the overall project. |
| C | Slack | 3 | These represent milestones or events within a project and are depicted as numbered boxes or circles. |
| D | Critical path activity | 4 | This involves executing tasks simultaneously to expedite project progress. |
1
a - 1, b - 3, c - 2 d - 4
2
a - 2, b - 4, c - 1, d - 3
3
a - 3, b - 4, c - 2, d - 1
4
a - 4, b - 2, c - 1 d - 3