Match the following

List I ( PERT term) List II ( Description)
A Nodes 1  It refers to tasks without slack, which are crucial for project timeline adherence.
B Fast-tracking 2 It denotes the duration by which a task can be delayed without affecting other tasks or the overall project.
C Slack 3 These represent milestones or events within a project and are depicted as numbered boxes or circles.
D Critical path activity 4 This involves executing tasks simultaneously to expedite project progress.

1
a - 1, b - 3, c - 2 d - 4
2
a - 2, b - 4, c - 1, d - 3
3
a - 3, b - 4, c - 2, d - 1
4
a - 4, b - 2, c - 1 d - 3